If the schedule performance index is less than one,  and if the cost performance index is greater than one then we can crash the tasks on the critical path to recover. If the cost performance index is also less than one, then what can be done?. Look at the flexibility matrix. If the flexibility matrix states that cost is flexible, still we can crash, else the options are only fast tracking or scope reduction. If you understand this then your knowledge of predictive project amanagement is good.